Sondu - Miriu Hydropower Project Sangoro Power Plant - Kshs 4,120,222,720
|
Creditor |
|
|
Creditor Category |
Bilateral |
|
Borrower |
Kenya Electricity Generatin |
|
Borrower Category |
Public Corporation |
|
Date Agreement Signed |
23-Jan-2007 |
|
Date Loan Matures |
20-Feb-2047 |
|
Original Agreement |
5,620,000 (JPK) |
|
Revised Amount |
4,247,215 (JPK) |
|
Amount in Kshs(2023) |
4,120,222,720.00 |
|
Interest Rate |
|
|
Terms |
|
Num |
Year |
Amount at Start |
Withdrawals |
Repayments |
Amount at end |
|---|---|---|---|---|---|
|
1 |
2023 |
(JPK) 3,539,300.00 |
0.00 |
141,572.00 |
3,397,728.00 |
|
2 |
2022 |
(JPK) 3,680,872.00 |
0.00 |
0.00 |
3,680,872.00 |
|
3 |
2021 |
(JPK) 3,822,444.00 |
141,572.00 |
3,822,444.00 |
3,680,872.00 |