Recurrent:

474,015,999.00

Development:

48,843,096,804.00

Allocation:

49,317,112,803.00

Previous Year Allocations

Num Year Recurrent Development Total
1 2026 KES 474,015,999.00 KES 48,843,096,804.00 KES 49,317,112,803.00
2 2025 KES 607,088,848.00 KES 37,009,443,854.00 KES 37,616,532,702.00
3 2024 KES 532,056,937.00 KES 38,435,900,000.00 KES 38,967,956,937.00
4 2023 KES 0.00 KES 39,780,000,000.00 KES 39,780,000,000.00

Recurrent KES 474,015,999.00
Development KES 48,843,096,804.00
Total KES 49,317,112,803.00

Recurrent KES 607,088,848.00
Development KES 37,009,443,854.00
Total KES 37,616,532,702.00

Recurrent KES 532,056,937.00
Development KES 38,435,900,000.00
Total KES 38,967,956,937.00

Recurrent KES 0.00
Development KES 39,780,000,000.00
Total KES 39,780,000,000.00
Allocations by Year
Sub-Programmes

Sub-Programs

Num Sub-Programme Budget
1 Rail Transport KES 49,317,112,803.00

Budget KES 49,317,112,803.00

Top 3 Recurrent Expenses

Num Unit Budget
1 Rail Transport Department KES 406,115,999.00
2 Kenya Railways Corporation KES 67,900,000.00
3 Rehabilitation of The Nairobi - Nanyuki MGR Branch Line-BETA KES 0.00

Recurrent Budget KES 406,115,999.00

Recurrent Budget KES 67,900,000.00

Top 3 Development Expenses

Num Unit Budget
1 Development of SGR Phase 2B and 2C - 369KM KES 20,843,070,172.00
2 Flood Mitigation Works KES 3,805,000,000.00
3 Acquisition of SGR Locomotives Wheelsets KES 2,758,000,000.00

Development Budget KES 20,843,070,172.00

Development Budget KES 3,805,000,000.00