Open Budget Kenya

 

Soin - Koru Dam - 2021

State Department

Ministry of Water, Sanitation & Irrigation

Programme

Water Storage and Flood Control

Sub Programme

Water Storage and Flood Control

Allocation:

KES 90,000,000.00 (D)

Previous Year Allocations

Num

Year

Total

1

2021

KES 90,000,000.00


Total Allocation KES 90,000,000.00
Changes in Allocations

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2021)

Target Yr (2022)

Target Yr (2023)

Dam constructed

% completion

10

35

60

Dam constructed

% completion


2021

10

2022

35

2023

60

Related Projects
Thwake MultiPurpose Water Development Program Phase I

% completion: 95


KES 9,623,000,000.00

(2021)

Water for Schools - ESP

No.of schools connected /supplied with water: 100


KES 270,000,000.00

(2021)

National Water Harvesting and Ground Water Exploitation

No.of surface water harvesting projects constructed: 75


KES 800,000,000.00

(2021)