Maintenance & Rehabilitation of NOFBI II Cable-BETA - 2025 |
|
---|---|
State Department |
|
Programme |
|
Sub Programme |
|
Allocation: |
KES 110,401,640.00 (D) |
Key Performance Indicators
Key Output |
KPI |
Target Yr (2025) |
Target Yr (2026) |
Target Yr (2027) |
---|---|---|---|---|
ICT Infrastructure Services |
% uptime of NOFBI II |
99.9 |
99.9 |
99.9 |
User Uploads
Previous Year Allocations
Num |
Year |
Recurrent |
Development |
Total |
---|---|---|---|---|
1 |
KES 0.00 |
KES 110,401,640.00 |
KES 110,401,640.00 |
|
2 |
KES 0.00 |
KES 617,000,000.00 |
KES 617,000,000.00 |
|
3 |
KES 0.00 |
KES 610,000,000.00 |
KES 610,000,000.00 |
|
4 |
KES 0.00 |
KES 632,000,000.00 |
KES 632,000,000.00 |
|
5 |
KES 0.00 |
KES 702,000,000.00 |
KES 702,000,000.00 |
No. of sites maintained: 850
KES 127,600,410.00
(2025)
% uptime of 630km main fiber network under (EARTTDFP) Programme: 100
KES 22,080,328.00
(2025)
% uptime of NOFBI II Expansion Cable: 99.9
KES 750,000,000.00
(2025)