Open Budget Kenya

 

Security in Penal Facilities - 2025

State Department

State Department for Correctional Services

Programme

Prison Services

Sub Programme

Offender Services

Allocation:

KES 33,540,000.00 (D)

Previous Year Allocations

Num

Year

Total

1

2026

KES 111,000,000.00

2

2025

KES 33,540,000.00

3

2024

KES 87,325,825.00

4

2023

KES 105,124,904.00

5

2022

KES 154,620,000.00

6

2021

KES 268,006,034.00


Total Allocation KES 111,000,000.00

Total Allocation KES 33,540,000.00

Total Allocation KES 87,325,825.00

Total Allocation KES 105,124,904.00

Total Allocation KES 154,620,000.00

Total Allocation KES 268,006,034.00
Changes in Allocations

Project Items

Num

Project

Amount

Year

1

Construction of perimeter Wall, Gate & Gate Lodge at Voi Prison

KES 0.00

2026

2

Completion of Administration Block at Thika Main Prison

KES 0.00

2026

3

Construction of reception block and armory at Nyandarua prison

KES 4,750,000.00

2026

4

Completion of a mixed block at Kaloleni Prison

KES 7,500,000.00

2026

5

Completion of Prisoners ward at Kangeta prison

KES 3,210,000.00

2026

6

Construction of mixed block at Rachuonyo prison

KES 4,000,000.00

2026

7

Construction of storeyed wards & admin offices Meru main prison

KES 7,900,000.00

2026

8

Completion of Perimeter Wall at Manyani GK Prison

KES 24,000,000.00

2026

9

Construction of security wall Muranga women prison

KES 0.00

2026

10

Construction of horse stables at Kamiti Medium

KES 2,000,000.00

2026

11

Construction of Perimeter Wall at Kiambu Prison

KES 0.00

2026

12

Construction of a Perimeter wall at Kericho Medium Prison

KES 11,230,000.00

2026

13

Construction of perimeter wall Malindi

KES 9,000,000.00

2026

14

Construction of perimeter walls Marsabit Prison

KES 0.00

2026

15

Construction of Perimeter Wall at Kajiado Prison

KES 4,500,000.00

2026

16

Construction of elevated watch towers at Kapsabet Prison

KES 0.00

2026

17

Construction of perimeter wall Hindi

KES 0.00

2026

18

Construction of phase 1 perimeter Wall Busia Prison

KES 4,800,000.00

2026

19

Construction Of Watch towers and main gate at Bomet Prison

KES 4,000,000.00

2026

20

Completion of Main Gate/Gate Lodge & Armoury at Rumuruti Prison

KES 2,600,000.00

2026

21

Completion of Gate Lodge, Armoury &Duty Office at Nyeri Medium Prison

KES 0.00

2026

22

Completion of Perimeter Wall at Eldoret Women Prison

KES 0.00

2026

23

Completion of Perimeter walls Machakos Women Prison

KES 1,500,000.00

2026

24

Completion of Gate Lodge at Garissa Medium Prison

KES 13,600,000.00

2026

25

Completion of phase 1 Perimeter Wall at Kilifi Prison

KES 6,410,000.00

2026

26

Construction of perimeter wall Hindi

KES 3,000,000.00

2025

27

Completion of Administration Block at Thika Main Prison

KES 2,250,000.00

2025

28

Construction of reception block and armory at Nyandarua prison

KES 1,250,000.00

2025

29

Completion of Perimeter Wall at Eldoret Women Prison

KES 1,750,000.00

2025

30

Completion of Prisoners ward at Kangeta prison

KES 1,605,000.00

2025

31

Construction of mixed block at Rachuonyo prison

KES 1,000,000.00

2025

32

Construction of storeyed wards & admin offices Meru main prison

KES 3,950,000.00

2025

33

Completion of Gate Lodge, Armoury &Duty Office at Nyeri Medium Prison

KES 1,965,000.00

2025

34

Construction of security wall Muranga women prison

KES 5,935,000.00

2025

35

Construction of horse stables at Kamiti Medium

KES 2,000,000.00

2025

36

Construction of Perimeter Wall at Kiambu Prison

KES 4,370,000.00

2025

37

Construction of perimeter Wall, Gate & Gate Lodge at Voi Prison

KES 2,050,000.00

2025

38

Construction of elevated watch towers at Kapsabet Prison

KES 800,000.00

2025

39

Construction of perimeter walls Marsabit Prison

KES 1,615,000.00

2025


2025 KES 3,000,000.00

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2025)

Target Yr (2026)

Target Yr (2027)

Correctional Services

No. of perimeter /security walls constructed.

18

19

19

Correctional Services

No. of main Gate /gate lodges and armories constructed.

7

9

11

Correctional Services

No. of blocks / wards constructed

6

8

10

Correctional Services

No. of perimeter /security walls constructed.


2025

18

2026

19

2027

19

Correctional Services

No. of main Gate /gate lodges and armories constructed.


2025

7

2026

9

2027

11

Correctional Services

No. of blocks / wards constructed


2025

6

2026

8

2027

10

Related Projects
YCTC Institutions

No. of YCTC boys undertaken through the treatment programme: 100


KES 13,567,341.00

(2025)

Headquarters Administrative Services - Prisons

No. of penal facilities supervised: 137


KES 1,952,331,120.00

(2025)

Regional Commands

No. of counties supervised by Regional Commanders: 47


KES 26,032,805,962.00

(2025)