Allocation:

KES 30,460,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2023)

Target Yr (2024)

Target Yr (2025)

Spot Improvement Works

No. of Km maintained

64

74

103

Spot Improvement Works

No. of Km maintained


2023

64

2024

74

2025

103

Previous Year Allocations

Num

Year

Total

1

2025

KES 44,257,215.00

2

2024

KES 35,539,716.00

3

2023

KES 30,460,000.00

4

2022

KES 84,150,000.00

5

2021

KES 234,000,000.00


Total Allocation KES 44,257,215.00

Total Allocation KES 35,539,716.00

Total Allocation KES 30,460,000.00

Total Allocation KES 84,150,000.00

Total Allocation KES 234,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Nuno-Modogashi Road

No. of Km constructed: 1


KES 0.00

(2023)

Mombasa Port Area Roads Development project

No. of Km constructed: 5


KES 43,000,000.00

(2023)

Northern Corridor Transport Improvement Project

No. of Km constructed: 1


KES 63,000,000.00

(2023)

© 2025 Copyright: Open Budget KE
Email: openbudgetke @ gmail.com