Allocation:

KES 8,570,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2023)

Target Yr (2024)

Target Yr (2025)

Spot Improvement XIII

No. of Km maintained

50

87

87

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2024

KES 0.00

KES 13,673,800.00

KES 13,673,800.00

2

2023

KES 0.00

KES 8,570,000.00

KES 8,570,000.00

3

2022

KES 0.00

KES 12,750,000.00

KES 12,750,000.00

4

2021

KES 0.00

KES 83,870,860.00

KES 83,870,860.00

Budgets
Related Projects
Nuno-Modogashi Road

No. of Km constructed: 1


KES 0.00

(2023)

Mombasa Port Area Roads Development project

No. of Km constructed: 5


KES 43,000,000.00

(2023)

Northern Corridor Transport Improvement Project

No. of Km constructed: 1


KES 63,000,000.00

(2023)