Open Budget Kenya

 

C509 Kiandongoro Forest Gate- Mutubio Forest Gate - 2023

State Department

State Department for Infrastructure

Programme

Road Transport

Sub Programme

Construction of Roads and Bridges

Allocation:

KES 10,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2023)

Target Yr (2024)

Target Yr (2025)

Kiandongoro Forest Gate-Mutubio Forest Gate

No. of Km constructed

6

10

12

Kiandongoro Forest Gate-Mutubio Forest Gate

No. of Km constructed


2023

6

2024

10

2025

12

Previous Year Allocations

Num

Year

Total

1

2025

KES 1,332,065.00

2

2024

KES 15,000,000.00

3

2023

KES 10,000,000.00

4

2022

KES 70,000,000.00

5

2021

KES 80,000,000.00


Total Allocation KES 1,332,065.00

Total Allocation KES 15,000,000.00

Total Allocation KES 10,000,000.00

Total Allocation KES 70,000,000.00

Total Allocation KES 80,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Nuno-Modogashi Road

No. of Km constructed: 1


KES 0.00

(2023)

Mombasa Port Area Roads Development project

No. of Km constructed: 5


KES 43,000,000.00

(2023)

Northern Corridor Transport Improvement Project

No. of Km constructed: 1


KES 63,000,000.00

(2023)

© 2025 Copyright: Open Budget KE