Development of Standard Gauge Railway - 2023

State Department

State Department for Transport

Programme

Rail Transport

Sub Programme

Rail Transport

Allocation:

KES 37,396,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2023)

Target Yr (2024)

Target Yr (2025)

Transhipment facility

% completion of transhipment of facility in Voi

50

100

100

Transhipment facility

% completion of transhipment of facility in Konza

10

50

70

Transhipment facility

% completion of transhipment of facility in Voi


2023

50

2024

100

2025

100

Transhipment facility

% completion of transhipment of facility in Konza


2023

10

2024

50

2025

70

Previous Year Allocations

Num

Year

Total

1

2023

KES 37,396,000,000.00


Total Allocation KES 37,396,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Critical Priority Projects-BETA

Km of MGR line constructed: 40.35


KES 2,786,000,000.00

(2023)

Rehabilitation of The Nairobi - Nanyuki MGR Branch Line-BETA

KM of MGR lines rehabilitated: 98


KES 284,000,000.00

KES 254,000,000.00

(2023)

Kisumu - Butere MGR-BETA

% rehabilitation of MGR line: 100


KES 48,000,000.00

(2023)