Nairobi Bus Rapid Transport Project - 2022 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 1,179,000,000.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2022) |
Target Yr (2023) |
Target Yr (2024) |
|---|---|---|---|---|
Nairobi Bus Rapid Transport Project |
% of works completed on BRT stations |
48 |
75 |
100 |
Nairobi Bus Rapid Transport Project |
% of works completed on BRT terminals |
80 |
95 |
100 |
Nairobi Bus Rapid Transport Project
% of works completed on BRT stations
2022
48
2023
75
2024
100
Nairobi Bus Rapid Transport Project
% of works completed on BRT terminals
2022
80
2023
95
2024
100
Previous Year Allocations
User Uploads
No.of monitoring and evaluation reports: 4
KES 260,509,039.00
(2022)