Open Budget Kenya

 

Construction of Foot Bridges - 2026

State Department

State Department for Public Works

Programme

Coastline Infrastructure and Pedestrian Access

Sub Programme

Pedestrian access

Allocation:

KES 19,720,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2026)

Target Yr (2027)

Target Yr (2028)

Footbridges

No. of footbridges constructed

8

5

2

Footbridges

No. of footbridges constructed


2026

8

2027

5

2028

2

Previous Year Allocations

Num

Year

Total

1

2026

KES 19,720,000.00

2

2024

KES 54,240,000.00

3

2023

KES 48,800,000.00

4

2022

KES 118,664,806.00

5

2021

KES 111,190,700.00


Total Allocation KES 19,720,000.00

Total Allocation KES 54,240,000.00

Total Allocation KES 48,800,000.00

Total Allocation KES 118,664,806.00

Total Allocation KES 111,190,700.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Structural Department

%level of supervision: 100


KES 117,015,769.00

(2026)

Construction of Ndau seawall

%level of completion: 50


KES 382,800,000.00

(2026)

Construction of New Mokowe Jetty

%level of completion: 100


KES 61,500,000.00

(2026)