Rehabilitation of Mtangawanda Jetty - 2021

State Department

State Department for Public Works

Programme

Coastline Infrastructure and Pedestrian Access

Sub Programme

Coastline Infrastructure Development

Allocation:

KES 10,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2021)

Target Yr (2022)

Target Yr (2023)

Mtangawanda Jetty

% of Jetty constructed/ Rehabilitated

100

-

-

Mtangawanda Jetty

% of Jetty constructed/ Rehabilitated


2021

100

2022

-

2023

-

Previous Year Allocations

Num

Year

Total

1

2023

KES 3,200,000.00

2

2022

KES 7,945,790.00

3

2021

KES 10,000,000.00


Total Allocation KES 3,200,000.00

Total Allocation KES 7,945,790.00

Total Allocation KES 10,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Structural Department

% of Jetty, sea wall and footbridge constructed/ rehabilitated: 100


KES 159,522,728.00

(2021)

Construction of New Mokowe Jetty

% of Jetty constructed/ Rehabilitated: 74


KES 14,300,000.00

(2021)

Construction of Foot Bridges

No. of footbridges constructed: 35


KES 111,190,700.00

(2021)