Moi's Bridge- Matunda Water and Sewerage Project - 2022 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 50,000,000.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2022) |
Target Yr (2023) |
Target Yr (2024) |
|---|---|---|---|---|
Water and sewerage services in Matunda town |
% project completion |
80 |
100 |
- |
Water and sewerage services in Matunda town
% project completion
2022
80
2023
100
2024
-
Previous Year Allocations
Num |
Year |
Total |
|---|---|---|
1 |
KES 259,000,000.00 |
|
2 |
KES 334,000,000.00 |
|
3 |
KES 200,000,000.00 |
|
4 |
KES 50,000,000.00 |
|
5 |
KES 83,000,000.00 |
User Uploads
Daily cubic meters supply: 4200
KES 68,584,532.00
(2022)