Mwea Irrigation Development project (Thiba Dam and Irrigation Area) - 2021

State Department

Ministry of Water, Sanitation & Irrigation

Programme

Irrigation and Land Reclamation

Sub Programme

Irrigation and Drainage

Allocation:

KES 3,301,000,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2021)

Target Yr (2022)

Target Yr (2023)

Acreage under irrigation

No. of Acres under irrigation

18524

35000

35000

Rice production

No.of Tons of paddy rice produced

85000

100000

100000

Dam constructed

% completion

90

-

-

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2022

KES 0.00

KES 1,415,000,000.00

KES 1,415,000,000.00

2

2021

KES 0.00

KES 3,301,000,000.00

KES 3,301,000,000.00

Budgets
Related Projects
Land Reclamation Services

% Completion rate of Land Reclamation Policy and Bill: 100


KES 46,077,813.00

(2021)

Land Reclamation (Land Degradation Assessment Program)

No. of feasibility studies: 4


KES 10,000,000.00

(2021)

Headquarters Administrative Services

No. of policies: 1


KES 245,426,561.00

(2021)