Mwea Irrigation Development project (Thiba Dam and Irrigation Area) - 2021 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 3,301,000,000.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2021) |
Target Yr (2022) |
Target Yr (2023) |
|---|---|---|---|---|
Acreage under irrigation |
No. of Acres under irrigation |
18524 |
19708 |
35000 |
Rice production |
No.of Tons of paddy rice produced |
85000 |
90000 |
100000 |
Dam constructed |
% completion |
90 |
100 |
- |
Acreage under irrigation
No. of Acres under irrigation
2021
18524
2022
19708
2023
35000
Rice production
No.of Tons of paddy rice produced
2021
85000
2022
90000
2023
100000
Dam constructed
% completion
2021
90
2022
100
2023
-
Previous Year Allocations
User Uploads
% Completion rate of Land Reclamation Policy and Bill: 100
KES 46,077,813.00
(2021)
No. of feasibility studies: 4
KES 10,000,000.00
(2021)