Open Budget Kenya

 

Rwabura Irrigation Development Project - 2022

State Department

Ministry of Water, Sanitation & Irrigation

Programme

Irrigation and Land Reclamation

Sub Programme

Irrigation and Drainage

Allocation:

KES 554,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2022)

Target Yr (2023)

Target Yr (2024)

Rwabura irrigation project

Acreage under irrigation

1000

-

-

Rwabura irrigation project

Acreage under irrigation


2022

1000

2023

-

2024

-

Previous Year Allocations

Num

Year

Total

1

2022

KES 554,000,000.00

2

2021

KES 131,000,000.00


Total Allocation KES 554,000,000.00

Total Allocation KES 131,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Land Reclamation Services

% completion rate of land reclamation policy and bill: 45


KES 47,167,782.00

(2022)

Land Reclamation (Land Degradation Assessment Program)

No. of assessment studies conducted: 1


KES 10,000,000.00

(2022)

Irrigation and Drainage Services

% project completion: 100


KES 96,310,900.00

(2022)

© 2025 Copyright: Open Budget KE
Email: openbudgetke @ gmail.com