Spate Irrigation for Climate Resilience in Samburu, Marsabit & Isiolo - 2021

State Department

Ministry of Water, Sanitation & Irrigation

Programme

Irrigation and Land Reclamation

Sub Programme

Irrigation and Drainage

Allocation:

KES 150,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2021)

Target Yr (2022)

Target Yr (2023)

Water storage for irrigation

cubic meters of water stored

2100000

2100000

3450000

Area under irrigation

No. of Acres under irrigation

1400

1400

2300

Water storage for irrigation

cubic meters of water stored


2021

2100000

2022

2100000

2023

3450000

Area under irrigation

No. of Acres under irrigation


2021

1400

2022

1400

2023

2300

Previous Year Allocations

Num

Year

Total

1

2022

KES 100,000,000.00

2

2021

KES 150,000,000.00


Total Allocation KES 100,000,000.00

Total Allocation KES 150,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Land Reclamation Services

% Completion rate of Land Reclamation Policy and Bill: 100


KES 46,077,813.00

(2021)

Land Reclamation (Land Degradation Assessment Program)

No. of feasibility studies: 4


KES 10,000,000.00

(2021)

Headquarters Administrative Services

No. of policies: 1