State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 1,475,412,022.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2026) |
Target Yr (2027) |
Target Yr (2028) |
|---|---|---|---|---|
Government Common Core Network (GCCN) services |
No. of additional MDAs connected |
30 |
35 |
35 |
Fibre Optic Infrastructure |
Km. of fibre installed |
13500 |
24145 |
- |
Fibre Optic Infrastructure |
% uptime of NOFBI internet |
99.99 |
99.99 |
99.99 |
Fibre Optic Infrastructure |
No. of cross-border points of connectivity |
2 |
2 |
3 |
Public Wi-Fi |
No. of Public Wi-Fi hotspots |
100 |
13356 |
- |
Digital Hubs |
No. of digital hubs established |
98 |
- |
- |
Digital Hubs |
No. of digital hubs equipped (With Virtual Desktop Infrastructure (VDI |
750 |
1450 |
- |
Connectivity to Naivasha Data Center |
% of operationalization of Naivasha Data Centre |
5 |
30 |
100 |
Government Common Core Network (GCCN) services
No. of additional MDAs connected
2026
30
2027
35
2028
35
Fibre Optic Infrastructure
Km. of fibre installed
2026
13500
2027
24145
2028
-
Fibre Optic Infrastructure
% uptime of NOFBI internet
2026
99.99
2027
99.99
2028
99.99
Fibre Optic Infrastructure
No. of cross-border points of connectivity
2026
2
2027
2
2028
3
Public Wi-Fi
No. of Public Wi-Fi hotspots
2026
100
2027
13356
2028
-
Digital Hubs
No. of digital hubs established
2026
98
2027
-
2028
-
Digital Hubs
No. of digital hubs equipped (With Virtual Desktop Infrastructure (VDI
2026
750
2027
1450
2028
-
Connectivity to Naivasha Data Center
% of operationalization of Naivasha Data Centre
2026
5
2027
30
2028
100
Previous Year Allocations
User Uploads
No. of sites maintained.: 892
(2026)
% uptime of NOFBI II: 99.9
(2026)