Open Budget Kenya

 

Construction of Headquarters and Satellite Campuses for KSA - 2023

State Department

State Department for Crop Development & Agricultural Research

Programme

Crop Development and Management

Sub Programme

Quality Assurance and Monitoring of Outreach Services

Allocation:

KES 75,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2023)

Target Yr (2024)

Target Yr (2025)

UGENYA Satellite CAMPUS 2 classroom and 2 ablution blocks

% completion

20

50

100

Borehole

% completion

-

50

100

Dining hall and Kitchen

% completion

-

-

100

AINABKOI Satellite CAMPUS Offices, workshops, training complex block.

No. of buses procured

1

1

-

Conference hall

% completion

50

100

-

NAKURU Satellite CAMPUS 50 self contained hostel rooms

% completion

20

50

100

Agro- processing and value addition unit

% completion

30

60

10

Purchase one school bus

No. of buses procured

1

-

-

50 self contained rooms hostel

% completion

20

50

100

NYERI Satellite CAMPUS 4 classrooms and 2 ablution blocks

% completion

70

100

-

20 metre cubic raised water tank

No. of completed water tank

1

-

-

THIKA Satellite CAMPUS 25 self contained hostel rooms

% completion

50

100

-

Procure one school bus

No. of buses procured

50

100

-

50 self-contained hostel rooms

% completion

30

60

100

Playing field and student centre

% completion

50

80

100

Student centre and one value addition unit.

% completion

25

50

100

Operational engineering workshops; soil science and computer laboratories.

% completion

30

75

100

UGENYA Satellite CAMPUS 2 classroom and 2 ablution blocks

% completion


2023

20

2024

50

2025

100

Borehole

% completion


2023

-

2024

50

2025

100

Dining hall and Kitchen

% completion


2023

-

2024

-

2025

100

AINABKOI Satellite CAMPUS Offices, workshops, training complex block.

No. of buses procured


2023

1

2024

1

2025

-

Conference hall

% completion


2023

50

2024

100

2025

-

NAKURU Satellite CAMPUS 50 self contained hostel rooms

% completion


2023

20

2024

50

2025

100

Agro- processing and value addition unit

% completion


2023

30

2024

60

2025

10

Purchase one school bus

No. of buses procured


2023

1

2024

-

2025

-

50 self contained rooms hostel

% completion


2023

20

2024

50

2025

100

NYERI Satellite CAMPUS 4 classrooms and 2 ablution blocks

% completion


2023

70

2024

100

2025

-

20 metre cubic raised water tank

No. of completed water tank


2023

1

2024

-

2025

-

THIKA Satellite CAMPUS 25 self contained hostel rooms

% completion


2023

50

2024

100

2025

-

Procure one school bus

No. of buses procured


2023

50

2024

100

2025

-

50 self-contained hostel rooms

% completion


2023

30

2024

60

2025

100

Playing field and student centre

% completion


2023

50

2024

80

2025

100

Student centre and one value addition unit.

% completion


2023

25

2024

50

2025

100

Operational engineering workshops; soil science and computer laboratories.

% completion


2023

30

2024

75

2025

100

Previous Year Allocations

Num

Year

Total

1

2025

KES 95,000,000.00

2

2024

KES 170,000,000.00

3

2023

KES 75,000,000.00

4

2022

KES 90,000,000.00

5

2021

KES 130,000,000.00


Total Allocation KES 95,000,000.00

Total Allocation KES 170,000,000.00

Total Allocation KES 75,000,000.00

Total Allocation KES 90,000,000.00

Total Allocation KES 130,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Headquarters Land and Crop Development Services

No. of dissemination fora held: 34


KES 346,854,765.00

(2023)

Agriculture Engineering Services

No. of dissemination fora held: 6


KES 35,214,919.00

(2023)

Agriculture Technology Development and Testing Stations

No. of ATDCs refurbished / developed: 1


KES 57,903,386.00

(2023)