Construction of Occupational Safety & Health- OSH-Institute-Phase I - 2022 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 106,360,000.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2022) |
Target Yr (2023) |
Target Yr (2024) |
|---|---|---|---|---|
Occupational Safety & Health- OSH-Institute Building |
% Completion |
89 |
100 |
- |
Occupational Safety & Health- OSH-Institute Building
% Completion
2022
89
2023
100
2024
-
Previous Year Allocations
Num |
Year |
Total |
|---|---|---|
1 |
KES 50,057,230.00 |
|
2 |
KES 94,755,400.00 |
|
3 |
KES 157,300,000.00 |
|
4 |
KES 106,360,000.00 |
|
5 |
KES 30,000,000.00 |