Allocation:

KES 566,500,000.00 (R)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2021)

Target Yr (2022)

Target Yr (2023)

TARDA Regional Resource Centre

% Completion

5.00%

5.00%

5.00%

TARDA - Integrated Regional Master Plan (IRMP)

% Completion

90.00%

95.00%

100.00%

Master Plan (IRMP)

% Completion

30.00%

90.00%

50.00%

Masinga Dam Resort (MDR) (8 executive suites)

% Completion

100.00%

-

-

Agricultural Technology Transferred to farmers

No. of farmers groups equipped with smart farming technology

25

30

35

TARDA Regional Resource Centre

% Completion


2021

5.00%

2022

5.00%

2023

5.00%

TARDA - Integrated Regional Master Plan (IRMP)

% Completion


2021

90.00%

2022

95.00%

2023

100.00%

Master Plan (IRMP)

% Completion


2021

30.00%

2022

90.00%

2023

50.00%

Masinga Dam Resort (MDR) (8 executive suites)

% Completion


2021

100.00%

2022

-

2023

-

Agricultural Technology Transferred to farmers

No. of farmers groups equipped with smart farming technology


2021

25

2022

30

2023

35

Previous Year Allocations

Num

Year

Total

1

2022

KES 713,600,000.00

2

2021

KES 566,500,000.00


Total Allocation KES 713,600,000.00

Total Allocation KES 566,500,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Conservation Department - Regional Development

% Completion: 100


KES 47,224,885.00

(2021)

Kerio Valley Development Authority

No. of water pans, weirs and dams constructed: 50


KES 371,180,000.00

(2021)

Lake Basin Development Authority (LBDA)

% completion: 20%


KES 348,210,000.00

(2021)