Allocation:

KES 10,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2021)

Target Yr (2022)

Target Yr (2023)

Oloyiangalani Oloshoibor Integrated water development and food security Project

% of completed desilted works at Oloshoibor dam

100%

-

-

Oloyiangalani Oloshoibor Integrated water development and food security Project

No. of household supplied with water

400

900

900

Oloyiangalani Oloshoibor Integrated water development and food security Project

No. of livestock supplied with water

30000

30000

30000

Oloyiangalani Oloshoibor Integrated water development and food security Project

% of completed desilted works at Oloshoibor dam


2021

100%

2022

-

2023

-

Oloyiangalani Oloshoibor Integrated water development and food security Project

No. of household supplied with water


2021

400

2022

900

2023

900

Oloyiangalani Oloshoibor Integrated water development and food security Project

No. of livestock supplied with water


2021

30000

2022

30000

2023

30000

Previous Year Allocations

Num

Year

Total

1

2022

KES 4,430,000.00

2

2021

KES 10,000,000.00


Total Allocation KES 4,430,000.00

Total Allocation KES 10,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Conservation Department - Regional Development

% Completion: 100


KES 47,224,885.00

(2021)

Kerio Valley Development Authority

No. of water pans, weirs and dams constructed: 50


KES 371,180,000.00

(2021)

Tana and Athi Rivers Development Authority (TARDA)

% Completion: 5.00%


KES 566,500,000.00

(2021)