Open Budget Kenya

 

Oloyiangalani Dam Development Project - 2021

State Department

State Department for Regional and Northern Corridor Development

Programme

Integrated Regional Development

Sub Programme

Integrated basin based Development

Allocation:

KES 10,000,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2021)

Target Yr (2022)

Target Yr (2023)

Oloyiangalani Oloshoibor Integrated water development and food security Project

% of completed desilted works at Oloshoibor dam

100%

-

-

Oloyiangalani Oloshoibor Integrated water development and food security Project

No. of household supplied with water

400

900

900

Oloyiangalani Oloshoibor Integrated water development and food security Project

No. of livestock supplied with water

30000

30000

30000

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2022

KES 0.00

KES 4,430,000.00

KES 4,430,000.00

2

2021

KES 0.00

KES 10,000,000.00

KES 10,000,000.00

Budgets
Related Projects
Conservation Department - Regional Development

% Completion: 100


KES 47,224,885.00

(2021)

Kerio Valley Development Authority

No. of water pans, weirs and dams constructed: 50


KES 371,180,000.00

(2021)

Tana and Athi Rivers Development Authority (TARDA)

% Completion: 5.00%


KES 566,500,000.00

(2021)

© 2025 Copyright: Open Budget KE
Email: openbudgetke @ gmail.com