Construction of MiritiniTreatment and Rehabilitation Center - 2022 |
|
---|---|
State Department |
|
Programme |
|
Sub Programme |
|
Allocation: |
KES 100,000,000.00 (D) |
Key Performance Indicators
Key Output |
KPI |
Target Yr (2022) |
Target Yr (2023) |
Target Yr (2024) |
---|---|---|---|---|
Miritini Treatment and Rehabilitation Services |
% Completion of the funded phase |
100 |
100 |
100 |
Miritini Treatment and Rehabilitation Services |
No. of persons rehabilitated |
10000 |
10000 |
10000 |
Previous Year Allocations
Num |
Year |
Recurrent |
Development |
Total |
---|---|---|---|---|
1 |
KES 0.00 |
KES 100,000,000.00 |
KES 100,000,000.00 |
|
2 |
KES 0.00 |
KES 100,000,000.00 |
KES 100,000,000.00 |