Open Budget Kenya

 

National Urban Transport Improvement Project (NUTRIP) - 2026

State Department

State Department for Infrastructure

Programme

Road Transport

Sub Programme

Construction of Roads and Bridges

Allocation:

KES 912,791,287.00 (D)

Previous Year Allocations

Num

Year

Total

1

2026

KES 912,791,287.00

2

2025

KES 161,535,893.00

3

2024

KES 320,000,000.00

4

2023

KES 540,000,000.00

5

2022

KES 272,286,599.00

6

2021

KES 720,000,000.00


Total Allocation KES 912,791,287.00

Total Allocation KES 161,535,893.00

Total Allocation KES 320,000,000.00

Total Allocation KES 540,000,000.00

Total Allocation KES 272,286,599.00

Total Allocation KES 720,000,000.00
Changes in Allocations

Project Items

Num

Project

Amount

Year

1

Headquarters

KES 40,000,000.00

2026

2

NUTRIP- James Gichuru junction - Rironi (Uhuru Highway) (26 km)

KES 872,791,287.00

2026

3

Headquarters

KES 22,080,332.00

2025

4

NUTRIP- James Gichuru junction - Rironi (Uhuru Highway) (26 km)

KES 139,455,561.00

2025


2026 KES 40,000,000.00

2025 KES 22,080,332.00

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2026)

Target Yr (2027)

Target Yr (2028)

National Urban Transport Improvement Project

No of Km Constructed

4

8

5

Training and capacity Building

No of workshop Conducted

30

40

30

National Urban Transport Improvement Project

No of Km Constructed


2026

4

2027

8

2028

5

Training and capacity Building

No of workshop Conducted


2026

30

2027

40

2028

30

Related Projects
Northern Corridor Transport Improvement Project

No of Km Constructed: 1.5


KES 108,836,105.00

(2026)

Kenya Transport Sector Support Programme

No of Km Constructed: 3


KES 324,957,197.00

(2026)

Mombasa Mariakani Highway Project

No of Km Constructed: 7


KES 3,693,576,235.00

(2026)