Open Budget Kenya

 

Muranga - Gitugi - 2022

State Department

State Department for Infrastructure

Programme

Road Transport

Sub Programme

Rehabilitation of Roads

Allocation:

KES 30,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2022)

Target Yr (2023)

Target Yr (2024)

Muranga - Gitugi

No. of Km rehabilitated

5

5

6

Muranga - Gitugi

No. of Km rehabilitated


2022

5

2023

5

2024

6

Previous Year Allocations

Num

Year

Total

1

2024

KES 70,028,101.00

2

2023

KES 60,090,000.00

3

2022

KES 30,000,000.00

4

2021

KES 60,000,000.00


Total Allocation KES 70,028,101.00

Total Allocation KES 60,090,000.00

Total Allocation KES 30,000,000.00

Total Allocation KES 60,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Nuno-Modogashi Road

No of Km Constructed: 2


KES 400,000,000.00

(2022)

Mombasa Port Area Roads Development project

No. of Km constructed: 4


KES 50,000,000.00

(2022)

Northern Corridor Transport Improvement Project

No. of Km constructed: 1


KES 50,000,000.00

(2022)

© 2025 Copyright: Open Budget KE
Email: openbudgetke @ gmail.com