Open Budget Kenya

 

Dualing of Ngong Road Phase II (Adams Arcade - Ngong Town- Kiserian, - 2022

State Department

State Department for Infrastructure

Programme

Road Transport

Sub Programme

Construction of Roads and Bridges

Allocation:

KES 150,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2022)

Target Yr (2023)

Target Yr (2024)

Adams Arcade - Ngong Town- Kiserian Road

No. of Km constructed

2

10

10

Adams Arcade - Ngong Town- Kiserian Road

No. of Km constructed


2022

2

2023

10

2024

10

Previous Year Allocations

Num

Year

Total

1

2024

KES 55,469,946.00

2

2023

KES 90,000,000.00

3

2022

KES 150,000,000.00

4

2021

KES 100,000,000.00


Total Allocation KES 55,469,946.00

Total Allocation KES 90,000,000.00

Total Allocation KES 150,000,000.00

Total Allocation KES 100,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Nuno-Modogashi Road

No of Km Constructed: 2


KES 400,000,000.00

(2022)

Mombasa Port Area Roads Development project

No. of Km constructed: 4


KES 50,000,000.00

(2022)

Northern Corridor Transport Improvement Project

No. of Km constructed: 1


KES 50,000,000.00

(2022)

© 2025 Copyright: Open Budget KE