Open Budget Kenya

 

Masalani - Kotile - Gamba - Malindi Road - 2025

State Department

State Department for Infrastructure

Programme

Road Transport

Sub Programme

Rehabilitation of Roads

Allocation:

KES 11,963,702.00 (D)

Previous Year Allocations

Num

Year

Total

1

2025

KES 11,963,702.00

2

2024

KES 22,886,368.00

3

2023

KES 27,540,000.00

4

2022

KES 27,000,000.00


Total Allocation KES 11,963,702.00

Total Allocation KES 22,886,368.00

Total Allocation KES 27,540,000.00

Total Allocation KES 27,000,000.00
Changes in Allocations

Project Items

Num

Project

Amount

Year

1

Masalani - Kotile - Gamba - Malindi Road

KES 0.00

2026

2

Masalani - Kotile - Gamba - Malindi Road

KES 11,963,702.00

2025

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2025)

Target Yr (2026)

Target Yr (2027)

Masalani - Kotile - Gamba - Malindi Road

No of Km Rehabilitated

0.5

-

-

Masalani - Kotile - Gamba - Malindi Road

No of Km Rehabilitated


2025

0.5

2026

-

2027

-

Related Projects
Northern Corridor Transport Improvement Project

No. of Km constructed: 1


KES 163,893,142.00

(2025)

Kenya Transport Sector Support Programme

No. of Km constructed: 2


KES 90,575,657.00

(2025)

National Urban Transport Improvement Project (NUTRIP)

No. of Km constructed: 1


KES 161,535,893.00