Open Budget Kenya

 

Biretwo Arror - Chesongoch (B126) Road (85km) - 2025

State Department

State Department for Infrastructure

Programme

Road Transport

Sub Programme

Construction of Roads and Bridges

Allocation:

KES 16,394,647.00 (D)

Previous Year Allocations

Num

Year

Total

1

2026

KES 14,733,439.00

2

2025

KES 16,394,647.00

3

2024

KES 15,000,000.00


Total Allocation KES 14,733,439.00

Total Allocation KES 16,394,647.00

Total Allocation KES 15,000,000.00
Changes in Allocations

Project Items

Num

Project

Amount

Year

1

Biretwo - Arror - Chesongoch (B126) Road (85km)

KES 14,733,439.00

2026

2

Biretwo -- Arror - Chesongoch (B126) Road (85km)

KES 16,394,647.00

2025

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2025)

Target Yr (2026)

Target Yr (2027)

Biretwo Arror - Chesongoch (B126) Road

No of Km Constructed

3

5

10

Biretwo Arror - Chesongoch (B126) Road

No of Km Constructed


2025

3

2026

5

2027

10

Related Projects
Northern Corridor Transport Improvement Project

No. of Km constructed: 1


KES 163,893,142.00

(2025)

Kenya Transport Sector Support Programme

No. of Km constructed: 2


KES 90,575,657.00

(2025)

National Urban Transport Improvement Project (NUTRIP)

No. of Km constructed: 1


KES 161,535,893.00

(2025)