Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2023) |
Target Yr (2024) |
Target Yr (2025) |
|---|---|---|---|---|
Irrigation water conveyance |
% completion of the project |
20 |
70 |
100 |
Irrigation water conveyance
% completion of the project
2023
20
2024
70
2025
100
Previous Year Allocations
User Uploads
No. of Hectares rehabilitated: 10
KES 45,035,097.00
KES 35,952,180.00
(2023)
No. of Assessment studies conducted: 2
KES 10,000,000.00
(2023)
Irrigation Projects Implemented Efficiently: 100
KES 61,536,455.00
KES 47,101,516.00
(2023)