Allocation:

KES 5,097,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2022)

Target Yr (2023)

Target Yr (2024)

Karimenu II dam

% project completion

70

100

-

Karimenu II dam

% project completion

70

100

-

Karimenu II dam

% project completion


2022

70

2023

100

2024

-

Karimenu II dam

% project completion


2022

70

2023

100

2024

-

Previous Year Allocations

Num

Year

Total

1

2025

KES 50,000,000.00

2

2024

KES 102,000,000.00

3

2023

KES 300,000,000.00

4

2022

KES 5,097,000,000.00

5

2021

KES 5,400,000,000.00


Total Allocation KES 50,000,000.00

Total Allocation KES 102,000,000.00

Total Allocation KES 300,000,000.00

Total Allocation KES 5,097,000,000.00

Total Allocation KES 5,400,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Water Resources - Pollution Control

No. of water quality monitoring reports: 25


KES 35,978,899.00

(2022)

Water Resources - Surface Water

No. of telemetric stations rehabilitated: 8


KES 50,712,748.00

(2022)

Water Resources

No. of M&E report on water quality produced: 4


KES 49,912,858.00

(2022)