Konza data Center & Smart City Facilities - 2021

State Department

State Department for Information Communication Technology

Programme

ICT Infrastructure Development

Sub Programme

ICT and BPO Development

Allocation:

KES 5,200,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2021)

Target Yr (2022)

Target Yr (2023)

Data centre and smart city facilities

% of data Centre completed

92

100

-

Data centre and smart city facilities

% of smart city facilities installed

80

100

-

Data centre and smart city facilities

% of data Centre completed


2021

92

2022

100

2023

-

Data centre and smart city facilities

% of smart city facilities installed


2021

80

2022

100

2023

-

Previous Year Allocations

Num

Year

Total

1

2025

KES 3,110,401,640.00

2

2024

KES 5,159,000,000.00

3

2023

KES 1,200,000,000.00

4

2022

KES 3,816,000,000.00

5

2021

KES 5,200,000,000.00


Total Allocation KES 3,110,401,640.00

Total Allocation KES 5,159,000,000.00

Total Allocation KES 1,200,000,000.00

Total Allocation KES 3,816,000,000.00

Total Allocation KES 5,200,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Maintenance & Rehabilitation of Last Mile County Connectivity Network

% of internet based 4000 network maintained/ rehabilitated: 100


KES 463,000,000.00

(2021)

Installation and Commissioning of Eldoret - Nadapal Fibre Optic Cable

No.of Km of fiber network from Eldoret to Nandapal laid: 315


KES 1,100,000,000.00

(2021)

Maintenance & Rehabilitation of NOFBI II Cable

% of NOFBI phase II network maintained/ rehabilitated: 100


KES 702,000,000.00