Djibouti Africa Regional Express (DARE) - 2021 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 50,000,000.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2021) |
Target Yr (2022) |
Target Yr (2023) |
|---|---|---|---|---|
Kenya - Djibouti undersea cable |
% of completion of works |
5 |
15 |
20 |
Kenya - Djibouti undersea cable
% of completion of works
2021
5
2022
15
2023
20
Previous Year Allocations
Num |
Year |
Total |
|---|---|---|
1 |
KES 24,600,000.00 |
|
2 |
KES 15,000,000.00 |
|
3 |
KES 40,000,000.00 |
|
4 |
KES 50,000,000.00 |
User Uploads
% of internet based 4000 network maintained/ rehabilitated: 100
KES 463,000,000.00
(2021)
No.of Km of fiber network from Eldoret to Nandapal laid: 315
KES 1,100,000,000.00
(2021)
% of NOFBI phase II network maintained/ rehabilitated: 100
KES 702,000,000.00
(2021)