National Grid System - 2024 |
|
---|---|
State Department |
|
Programme |
|
Sub Programme |
|
Allocation: |
KES 5,602,191,396.00 (R) |
Key Performance Indicators
Key Output |
KPI |
Target Yr (2024) |
Target Yr (2025) |
Target Yr (2026) |
---|---|---|---|---|
Technical Validation , monitoring and evaluation services |
Technical Validation reports |
4 |
4 |
4 |
Power transmission infrastructure monitoring reports |
No. of quarterly technical transmission line and associated substations reports |
4 |
4 |
4 |
Previous Year Allocations
Num |
Year |
Recurrent |
Development |
Total |
---|---|---|---|---|
1 |
KES 3,245,000,000.00 |
KES 0.00 |
KES 3,245,000,000.00 |
|
2 |
KES 10,917,000,000.00 |
KES 0.00 |
KES 10,917,000,000.00 |
|
3 |
KES 3,844,711,907.00 |
KES 0.00 |
KES 3,844,711,907.00 |
|
4 |
KES 5,602,191,396.00 |
KES 0.00 |
KES 5,602,191,396.00 |