Geothermal and Coal Resource Exploration and Development - 2025 |
|
---|---|
State Department |
|
Programme |
|
Sub Programme |
|
Allocation: |
KES 1,846,102,298.00 (R) |
Key Performance Indicators
Key Output |
KPI |
Target Yr (2025) |
Target Yr (2026) |
Target Yr (2027) |
---|---|---|---|---|
Geothermal Power Services |
Percentage (%) Completion of 63MW Olkaria 1 Rehabilitation Power plant |
80 |
100 |
100 |
Geothermal Power Services |
Percentage (%) Completion of 40MW Olkaria 1 Turbine Uprating |
12 |
70 |
70 |
User Uploads
Previous Year Allocations
Num |
Year |
Recurrent |
Development |
Total |
---|---|---|---|---|
1 |
KES 1,846,102,298.00 |
KES 0.00 |
KES 1,846,102,298.00 |
|
2 |
KES 1,529,736,011.00 |
KES 0.00 |
KES 1,529,736,011.00 |
|
3 |
KES 1,904,921,265.00 |
KES 0.00 |
KES 1,904,921,265.00 |
|
4 |
KES 1,907,000,000.00 |
KES 0.00 |
KES 1,907,000,000.00 |
|
5 |
KES 1,882,000,000.00 |
KES 0.00 |
KES 1,882,000,000.00 |
Percentage (%) completion of KenGen geothermal training centre: 80
KES 212,000,000.00
(2025)