Geothermal and Coal Resource Exploration and Development - 2025 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 1,846,102,298.00 (R) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2025) |
Target Yr (2026) |
Target Yr (2027) |
|---|---|---|---|---|
Geothermal Power Services |
Percentage (%) Completion of 63MW Olkaria 1 Rehabilitation Power plant |
80 |
95 |
100 |
Geothermal Power Services |
Percentage (%) Completion of 40MW Olkaria 1 Turbine Uprating |
12 |
40 |
70 |
Geothermal Power Services
Percentage (%) Completion of 63MW Olkaria 1 Rehabilitation Power plant
2025
80
2026
95
2027
100
Geothermal Power Services
Percentage (%) Completion of 40MW Olkaria 1 Turbine Uprating
2025
12
2026
40
2027
70
Previous Year Allocations
Num |
Year |
Total |
|---|---|---|
1 |
KES 1,846,102,298.00 |
|
2 |
KES 1,529,736,011.00 |
|
3 |
KES 1,904,921,265.00 |
|
4 |
KES 1,907,000,000.00 |
|
5 |
KES 1,882,000,000.00 |
User Uploads
Percentage (%) completion of KenGen geothermal training centre: 80
KES 212,000,000.00
(2025)