Rural Electrification and Renewable Energy Corporation - 2025

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

Rural Electrification

Allocation:

KES 3,832,000,000.00 (R)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2025)

Target Yr (2026)

Target Yr (2027)

Power connectivity services

No. of New Customers Connected

480000

480000

480000

Power connectivity services

No. of Street Lights Erected

6500

6500

6500

Power connectivity services

No. of public facilities connected to electricity

320

360

400

Power connectivity services

No. of Transformers Installed in constituencies

200

250

300

Power connectivity services

No. of New Hybrid Mini-grids Installed

100

-

-

Power connectivity services

No. of New Customers Connected


2025

480000

2026

480000

2027

480000

Power connectivity services

No. of Street Lights Erected


2025

6500

2026

6500

2027

6500

Power connectivity services

No. of public facilities connected to electricity


2025

320

2026

360

2027

400

Power connectivity services

No. of Transformers Installed in constituencies


2025

200

2026

250

2027

300

Power connectivity services

No. of New Hybrid Mini-grids Installed


2025

100

2026

-

2027

-

Previous Year Allocations

Num

Year

Total

1

2025

KES 3,832,000,000.00

2

2024

KES 2,252,000,000.00

3

2023

KES 1,780,000,000.00

4

2022

KES 1,328,390,083.00

5

2021

KES 884,000,000.00


Total Allocation KES 3,832,000,000.00

Total Allocation KES 2,252,000,000.00

Total Allocation KES 1,780,000,000.00

Total Allocation KES 1,328,390,083.00

Total Allocation KES 884,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
National Grid System

Km of Transmission Lines Constructed: 248


KES 5,879,816,289.00

(2025)

SonduHomabay Ndhiwa Awendo Electrification Project-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 80


KES 693,696,723.00

(2025)

Olkaria Lessos Kisumu Power Lines Construction Project

Percentage completion of transmission line and associated substations: 50


KES 506,086,029.00

(2025)