Allocation:

KES 5,771,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2022)

Target Yr (2023)

Target Yr (2024)

Power generation capacity

No. of wells drilled

11

13

13

Power generation capacity

MW of steam equivalent (Cumulative)

61.76

94.26

126.76

Power generation capacity

No. of wells drilled


2022

11

2023

13

2024

13

Power generation capacity

MW of steam equivalent (Cumulative)


2022

61.76

2023

94.26

2024

126.76

Previous Year Allocations

Num

Year

Total

1

2025

KES 2,806,000,000.00

2

2024

KES 4,134,000,000.00

3

2023

KES 4,723,000,000.00

4

2022

KES 5,771,000,000.00

5

2021

KES 2,398,000,000.00


Total Allocation KES 2,806,000,000.00

Total Allocation KES 4,134,000,000.00

Total Allocation KES 4,723,000,000.00

Total Allocation KES 5,771,000,000.00

Total Allocation KES 2,398,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Geothermal and Coal Resource Exploration and Development

Geothermal Resources Licencees Compliance Report: 1


KES 1,907,000,000.00

(2022)

Olkaria I and IV

Percentage completion of 83.3 MW Power plant: 100


KES 2,000,000,000.00

(2022)

Menengai Geothermal Development Project

No. of wells drilled: 1


KES 1,200,000,000.00

(2022)