Open Budget Kenya

 

Olkaria Lessos Kisumu Power Lines Construction Project - 2025

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

National Grid System

Allocation:

KES 506,086,029.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2025)

Target Yr (2026)

Target Yr (2027)

Power transmission infrastructure

Percentage completion of transmission line and associated substations

50

80

100

Power transmission infrastructure

Percentage completion of transmission line and associated substations


2025

50

2026

80

2027

100

Previous Year Allocations

Num

Year

Total

1

2025

KES 506,086,029.00

2

2024

KES 451,500,000.00

3

2023

KES 442,000,000.00

4

2022

KES 1,700,000,000.00

5

2021

KES 961,000,000.00


Total Allocation KES 506,086,029.00

Total Allocation KES 451,500,000.00

Total Allocation KES 442,000,000.00

Total Allocation KES 1,700,000,000.00

Total Allocation KES 961,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
National Grid System

Km of Transmission Lines Constructed: 248


KES 5,879,816,289.00

(2025)

SonduHomabay Ndhiwa Awendo Electrification Project-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 80


KES 693,696,723.00

(2025)

Turkwell- Ortum- Kitale

Percentage completion of transmission line and associated substations: 100


KES 168,334,901.00

(2025)