Eastern Electricity Highway Project (Ethiopia- Kenya Interconnector) - 2022 |
|
---|---|
State Department |
|
Programme |
|
Sub Programme |
|
Allocation: |
KES 8,128,000,000.00 (D) |
Key Performance Indicators
Key Output |
KPI |
Target Yr (2022) |
Target Yr (2023) |
Target Yr (2024) |
---|---|---|---|---|
Power transmission infrastructure |
Percentage completion of 641km 500kV HVDC transmission line and the associated converter substation |
100 |
- |
- |
Previous Year Allocations
Num |
Year |
Recurrent |
Development |
Total |
---|---|---|---|---|
1 |
KES 0.00 |
KES 7,222,000,000.00 |
KES 7,222,000,000.00 |
|
2 |
KES 0.00 |
KES 8,128,000,000.00 |
KES 8,128,000,000.00 |
|
3 |
KES 0.00 |
KES 1,975,000,000.00 |
KES 1,975,000,000.00 |
|
4 |
KES 0.00 |
KES 746,800,000.00 |
KES 746,800,000.00 |