Menengai Geothermal Development Project - 2021 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 1,640,000,000.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2021) |
Target Yr (2022) |
Target Yr (2023) |
|---|---|---|---|---|
Menengai Geothermal Well |
No. of wells drilled |
1 |
3 |
3 |
Menengai Geothermal Well |
MWe steam equivalent produced |
177.3 |
186.2 |
195.1 |
Menengai Geothermal Well
No. of wells drilled
2021
1
2022
3
2023
3
Menengai Geothermal Well
MWe steam equivalent produced
2021
177.3
2022
186.2
2023
195.1
Previous Year Allocations
Num |
Year |
Total |
|---|---|---|
1 |
KES 1,950,000,000.00 |
|
2 |
KES 2,162,000,000.00 |
|
3 |
KES 1,200,000,000.00 |
|
4 |
KES 1,200,000,000.00 |
|
5 |
KES 1,640,000,000.00 |
User Uploads
No. of geotechnical study reports on coal and geothermal: 4
KES 1,882,000,000.00
(2021)