Menengai Geothermal Development Project - 2023 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 1,200,000,000.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2023) |
Target Yr (2024) |
Target Yr (2025) |
|---|---|---|---|---|
Menengai geothermal power project |
No of Well drilled |
2 |
2 |
2 |
Menengai geothermal power project |
MW of steam equivalent( cumulative) |
181.7 |
191.7 |
201.7 |
Menengai geothermal power project
No of Well drilled
2023
2
2024
2
2025
2
Menengai geothermal power project
MW of steam equivalent( cumulative)
2023
181.7
2024
191.7
2025
201.7
Previous Year Allocations
Num |
Year |
Total |
|---|---|---|
1 |
KES 1,950,000,000.00 |
|
2 |
KES 2,162,000,000.00 |
|
3 |
KES 1,200,000,000.00 |
|
4 |
KES 1,200,000,000.00 |
|
5 |
KES 1,640,000,000.00 |
User Uploads
Geotechical Study Reports: 2
KES 1,904,921,265.00
(2023)
Percentage completion of 83.3MW Olkaria 1 Unit 6 Power plant: 100
KES 1,000,000,000.00
(2023)