Allocation:

KES 5,803,000,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2022)

Target Yr (2023)

Target Yr (2024)

Power Connection

No. of new customers connected to electricity

100000

-

-

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2021

KES 0.00

KES 6,493,000,000.00

KES 6,493,000,000.00

2

2022

KES 0.00

KES 5,803,000,000.00

KES 5,803,000,000.00

3

2023

KES 0.00

KES 11,400,000,000.00

KES 11,400,000,000.00

4

2024

KES 0.00

KES 3,388,000,000.00

KES 3,388,000,000.00