Multi-National Kenya-TZ Power Interconnection Project-BETA - 2023

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

National Grid System

Allocation:

KES 936,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2023)

Target Yr (2024)

Target Yr (2025)

Power transmission infrastructure

Percentage completion of transmission line and associated substations

98

100

-

Power transmission infrastructure

Percentage completion of transmission line and associated substations


2023

98

2024

100

2025

-

Previous Year Allocations

Num

Year

Total

1

2025

KES 99,067,908.00

2

2024

KES 292,900,000.00

3

2023

KES 936,000,000.00

4

2022

KES 1,266,000,000.00

5

2021

KES 948,000,000.00


Total Allocation KES 99,067,908.00

Total Allocation KES 292,900,000.00

Total Allocation KES 936,000,000.00

Total Allocation KES 1,266,000,000.00

Total Allocation KES 948,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
National Grid System

No. of quarterly technical monitoring and validation reports of energy projects: 4


KES 3,844,711,907.00

(2023)

Nanyuki-Isiolo- Meru-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 100


KES 235,000,000.00

(2023)

SonduHomabay Ndhiwa Awendo Electrification Project-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 100


KES 464,000,000.00