Open Budget Kenya

 

Mariakani Substation - 2021

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

National Grid System

Allocation:

KES 1,064,000,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2021)

Target Yr (2022)

Target Yr (2023)

400/220kV Substation

% completion

100

-

-

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2025

KES 0.00

KES 508,588,391.00

KES 508,588,391.00

2

2024

KES 0.00

KES 275,000,000.00

KES 275,000,000.00

3

2023

KES 0.00

KES 976,000,000.00

KES 976,000,000.00

4

2022

KES 0.00

KES 25,000,000.00

KES 25,000,000.00

5

2021

KES 0.00

KES 1,064,000,000.00

KES 1,064,000,000.00

Budgets
Related Projects
National Grid System

No. of public awareness forums conducted: 30


KES 3,245,000,000.00

(2021)

Nanyuki-Isiolo- Meru

% completion: 100


KES 340,000,000.00

(2021)

SonduHomabay Ndhiwa Awendo Electrification Project

% completion: 100


KES 514,000,000.00

(2021)