Open Budget Kenya

 

Rabai - Malindi- Garsen - Lamu - 2021

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

National Grid System

Allocation:

KES 40,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2021)

Target Yr (2022)

Target Yr (2023)

Transmission line and associated substations

Percentage of completion

100

-

-

Transmission line and associated substations

Percentage of completion


2021

100

2022

-

2023

-

Previous Year Allocations

Num

Year

Total

1

2021

KES 40,000,000.00


Total Allocation KES 40,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
National Grid System

No. of public awareness forums conducted: 30


KES 3,245,000,000.00

(2021)

Nanyuki-Isiolo- Meru

% completion: 100


KES 340,000,000.00

(2021)

SonduHomabay Ndhiwa Awendo Electrification Project

% completion: 100


KES 514,000,000.00

(2021)

© 2025 Copyright: Open Budget KE
Email: openbudgetke @ gmail.com