Open Budget Kenya

 

Menengai - Soilo - 2023

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

National Grid System

Allocation:

KES 112,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2023)

Target Yr (2024)

Target Yr (2025)

Power transmission infrastructure

% completion of project

100

-

-

Power transmission infrastructure

% completion of project


2023

100

2024

-

2025

-

Previous Year Allocations

Num

Year

Total

1

2023

KES 112,000,000.00


Total Allocation KES 112,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
National Grid System

No. of quarterly technical monitoring and validation reports of energy projects: 4


KES 3,844,711,907.00

(2023)

Nanyuki-Isiolo- Meru-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 100


KES 235,000,000.00

(2023)

SonduHomabay Ndhiwa Awendo Electrification Project-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 100


KES 464,000,000.00

(2023)