Open Budget Kenya

 

Electrification of Public Facilities - 2024

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

Rural Electrification

Allocation:

KES 3,482,330,497.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2024)

Target Yr (2025)

Target Yr (2026)

Power connectivity

No. of additional public facilities connected to electricity

2,573

3,627

3,627

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2024

KES 0.00

KES 3,482,330,497.00

KES 3,482,330,497.00

2

2023

KES 0.00

KES 3,471,000,000.00

KES 3,471,000,000.00

3

2022

KES 0.00

KES 4,841,000,000.00

KES 4,841,000,000.00

4

2021

KES 0.00

KES 6,263,000,000.00

KES 6,263,000,000.00

Budgets
Related Projects
National Grid System

Technical Validation reports: 4


KES 5,602,191,396.00

(2024)

Nanyuki-Isiolo- Meru-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 100


KES 96,600,000.00

(2024)

SonduHomabay Ndhiwa Awendo Electrification Project-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 100


KES 373,800,000.00

(2024)