Nuclear Power Plant Siting - 2024 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 140,000,000.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2024) |
Target Yr (2025) |
Target Yr (2026) |
|---|---|---|---|---|
Nuclear power plant site |
% completion of nuclear site, environment Impact Assessment |
100 |
- |
- |
Nuclear power plant site |
% completion of site characterization report |
90 |
100 |
- |
Nuclear power plant site |
% completion of land acquisition |
50 |
75 |
100 |
Nuclear power plant site
% completion of nuclear site, environment Impact Assessment
2024
100
2025
-
2026
-
Nuclear power plant site
% completion of site characterization report
2024
90
2025
100
2026
-
Nuclear power plant site
% completion of land acquisition
2024
50
2025
75
2026
100
Previous Year Allocations
Num |
Year |
Total |
|---|---|---|
1 |
KES 54,769,250.00 |
|
2 |
KES 140,000,000.00 |
|
3 |
KES 208,000,000.00 |
|
4 |
KES 250,000,000.00 |
|
5 |
KES 100,000,000.00 |
User Uploads
No. of Research and Monitoring of Geotechnical Study Reports: 4
KES 1,529,736,011.00
(2024)
Percentage completion of 83.3MW Olkaria 1 Unit 6 Power plant: 100
KES 27,500,000.00
(2024)