Open Budget Kenya

 

Strategic Environmental Assessment - 2022

State Department

Ministry of Energy

Programme

Power Generation

Sub Programme

Development of Nuclear Energy

Allocation:

KES 50,000,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2022)

Target Yr (2023)

Target Yr (2024)

Sustainable, well conserved and maintained nuclear energy sites

Percentage completion of Implementation of Environmental Impact Assessment Report recommendations

70

100

100

Sustainable, well conserved and maintained nuclear energy sites

Percentage completion of Environmental impact assessment Report for identified sites

23.68

96.48

96.48

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2024

KES 0.00

KES 35,000,000.00

KES 35,000,000.00

2

2023

KES 0.00

KES 80,000,000.00

KES 80,000,000.00

3

2022

KES 0.00

KES 50,000,000.00

KES 50,000,000.00

4

2021

KES 0.00

KES 115,000,000.00

KES 115,000,000.00

Budgets
Related Projects
Geothermal and Coal Resource Exploration and Development

Geothermal Resources Licencees Compliance Report: 1


KES 1,907,000,000.00

(2022)

Bogoria Silali Geothermal Project

No. of wells drilled: 11


KES 5,771,000,000.00

(2022)

Olkaria I and IV

Percentage completion of 83.3 MW Power plant: 100


KES 2,000,000,000.00

(2022)