Open Budget Kenya

 

Solar PV installation on Institutions and or community boreholes in - 2024

State Department

Ministry of Energy

Programme

Alternative Energy Technologies

Sub Programme

Alternative Energy Technologies

Allocation:

KES 50,000,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2024)

Target Yr (2025)

Target Yr (2026)

Power connectivity

% of previously installed solar PV system in public institutions

100

100

100

Power connectivity

No. of community boreholes /Public institutions connected with solar PVs and desalination in off grid areas.

50

50

50

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2024

KES 0.00

KES 50,000,000.00

KES 50,000,000.00

2

2023

KES 0.00

KES 104,000,000.00

KES 104,000,000.00

3

2022

KES 0.00

KES 80,000,000.00

KES 80,000,000.00

Budgets
Related Projects
Alternative Energy Technologies

No of Supervision reports: 4


KES 68,716,719.00

(2024)

Hydro dams Water catchment re- afforestation

No. of hectares of hydro power dams water catchment re afforested and maintained: 1,000,000


KES 164,000,000.00

(2024)

Development of Community Small Hydro Power projects

No of Community small hydro power projects supported: 1


KES 20,000,000.00

(2024)