Open Budget Kenya

 

Installation of Transformers in Constituencies - 2024

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

Rural Electrification

Allocation:

KES 1,536,000,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2024)

Target Yr (2025)

Target Yr (2026)

Power Connectivity

No. of additional transformers installed in constituencies

858

1,142

1,142

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2024

KES 0.00

KES 1,536,000,000.00

KES 1,536,000,000.00

2

2023

KES 0.00

KES 2,029,000,000.00

KES 2,029,000,000.00

3

2022

KES 0.00

KES 1,000,000,000.00

KES 1,000,000,000.00

4

2021

KES 0.00

KES 598,000,000.00

KES 598,000,000.00

Budgets
Related Projects
National Grid System

Technical Validation reports: 4


KES 5,602,191,396.00

(2024)

Nanyuki-Isiolo- Meru-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 100


KES 96,600,000.00

(2024)

SonduHomabay Ndhiwa Awendo Electrification Project-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 100


KES 373,800,000.00

(2024)

© 2025 Copyright: Open Budget KE
Email: openbudgetke @ gmail.com