Open Budget Kenya

 

Nairobi City Centre E.H.V & 66KV Network Upgrade & Reinforcement - 2021

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

National Grid System

Allocation:

KES 1,000,000,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2021)

Target Yr (2022)

Target Yr (2023)

Transmission line and associated sub-stations

Percentage of completion

50

100

100

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2021

KES 0.00

KES 1,000,000,000.00

KES 1,000,000,000.00

Budgets
Related Projects
National Grid System

No. of public awareness forums conducted: 30


KES 3,245,000,000.00

(2021)

Nanyuki-Isiolo- Meru

% completion: 100


KES 340,000,000.00

(2021)

SonduHomabay Ndhiwa Awendo Electrification Project

% completion: 100


KES 514,000,000.00

(2021)