Allocation:

KES 1,000,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2021)

Target Yr (2022)

Target Yr (2023)

Transmission line and associated sub-stations

Percentage of completion

50

85

100

Transmission line and associated sub-stations

Percentage of completion


2021

50

2022

85

2023

100

Previous Year Allocations

Num

Year

Total

1

2021

KES 1,000,000,000.00


Total Allocation KES 1,000,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
National Grid System

No. of public awareness forums conducted: 30


KES 3,245,000,000.00

(2021)

Nanyuki-Isiolo- Meru

% completion: 100


KES 340,000,000.00

(2021)

SonduHomabay Ndhiwa Awendo Electrification Project

% completion: 100


KES 514,000,000.00

(2021)

© 2025 Copyright: Open Budget KE
Email: openbudgetke @ gmail.com